VA contract 36C25626P0523: Air emission testing for three natural gas generators
Goodwin Facilities Solutions, LLC held VA contract 36C25626P0523 for air emission testing for three natural gas generators in Pineville, LA. It started on Apr 2, 2026, and $32,760 has been obligated so far. The VA received 2 offers. This contract ended on Aug 31, 2026.
| Contract number | 36C25626P0523 |
|---|---|
| Solicitation number | 36C25626Q0490 |
| Contract holder | Goodwin Facilities Solutions, LLC |
| Holder UEI | JV58YBBCV728 |
| Description | Air emission testing for three natural gas generators |
| Location | Pineville, LA |
| Contracting office | VA Network Contract Office 16 (36C256) |
| Obligated to date | $32,760 |
| Start date | Apr 2, 2026 |
| Current end date | Aug 31, 2026 |
| Offers received | 2 |
| Set-aside | Service-disabled veteran-owned small business (SDVOSB) set-aside |
| Competition | Competed among eligible businesses (set-aside) |
| Kind of work | Maintenance repair |
| Official record | USAspending.gov |
Details come from the official record on USAspending.gov. Confirm them there before relying on them.
Other VA HVAC and plumbing contracts in Pineville, LA
- 36C25626P0490: Compressor replacement, $219,970, ended May 1, 2026
- 36C25625C0023: 500T chiller rental, $1.2 million, ends Mar 2, 2027
- 36C25624P1373: Base contract to perform inspection, tuning, testing, calibrating, and adjustments of burners and boiler plant controls, $18,277, ended Aug 29, 2025
- 36C25624C0069: Emergency chiller #2 repairs, $2.2 million, ended Mar 2, 2025
- 36C25624C0020: Project 502-21-110 (construction) - replace chiller #3, $1.6 million, ended Oct 12, 2025
- 36C25624P0336: Installation of steam condensate LINER-502, $98,755, ended Jun 30, 2024
- 36C25623P0877: Taco rotator replacement pump services, $17,848, ended Sep 30, 2023
- 36C25623P0844: Chilled water coils replacement x 2, $26,917, ended Aug 30, 2023
Other VA contracts held by Goodwin Facilities Solutions, LLC
- 36C25626C0010: Install isolation valves on domestic water system, B1, $379,535, ended Sep 28, 2026
- 36C25625C0040: 667-25-200 replace the 1ST and 2ND floor boiler serving building 5, $459,352, ended Jan 11, 2026
- 36C25625C0038: Project 667-25-185 install vav boxes in surgery storage, Shreveport, la, $100,000, ended Oct 31, 2025
- 36C25625N0619: EO14042 sps steam quality service, $8,913, ended Apr 9, 2025
- 36C25625N0200: Sps steam quality service, $17,826, ended Feb 28, 2025
- 36C25624C0078: Emergency steam line repair, $335,538, ended Jun 20, 2025
- 36C25624C0059: 1254-21 HVAC room conversion, $22,550, ended Oct 15, 2024
- 36C25624N0640: EO14042 sps steam quality service, $8,913, ended Apr 9, 2025