VA HVAC and plumbing contracts in Kansas City, MO
VA facilities in Kansas City, Missouri have awarded 17 heating, cooling and plumbing contracts since October 2018, worth $26.0 million. No recurring service contracts end in the next 18 months. Most of this work is awarded by VA Network Contract Office 15 (36C255). Of the 12 contracts with bid counts, 5 (41%) drew a single bid. Contracts here start most often in September.
Which contracts in Kansas City end soon?
No recurring service contracts end in the next 18 months.
Who has done this work in Kansas City?
- Ljbco Group LLC: 4 contracts
- Onsite Construction Group LLC: 3 contracts
- Pro-mechanical LLC: 3 contracts
- Caldaia Controls LLC: 1 contract
- Vazquez Commercial Contracting, LLC: 1 contract
- Cullum And Brown Of Kansas City Inc.: 1 contract
- Cullum & Brown, Inc.: 1 contract
- Wfv Construction, LLC: 1 contract
- Saw Contracting, Inc.: 1 contract
- Destination Zero, LLC: 1 contract
All contracts in Kansas City since 2018
| Contract | Description | Company | Obligated | Start | End |
|---|---|---|---|---|---|
| 36C25526P0344 | Emergent services boiler | Onsite Construction Group LLC | $1.3 million | Sep 10, 2026 | Jan 31, 2027 |
| 36C25524C0022 | Project 589-24-111- replace 800 feet of watermain piping as an emergency action | Onsite Construction Group LLC | $550,118 | Feb 16, 2024 | May 16, 2024 |
| 36C25523C0097 | 589-22-420:RENOVATE 4 east for progressive care unit | Onsite Construction Group LLC | $7.6 million | Oct 11, 2023 | Sep 1, 2025 |
| 36C25522P0285 | Emergency chiller rental for the kansas city VAMC | Pro-mechanical LLC | $40,900 | Mar 28, 2022 | Jul 31, 2022 |
| 36C25521P0723 | Boiler safety device inspection and certification | Caldaia Controls LLC | $361,369 | Sep 22, 2021 | Sep 21, 2026 |
| 36C25521P0483 | Kc VA medical center emergency cooling tower repair | Pro-mechanical LLC | $175,062 | Jun 18, 2021 | Sep 30, 2021 |
| 36C25521N0234 | 589-19-102 extend chilled water loop NCO15 HVAC specialty MATOC | Ljbco Group LLC | $3.5 million | Mar 24, 2021 | May 16, 2022 |
| 36C25520N0226 | Renovate 9 east NCO15 HVAC specialty MATOC | Ljbco Group LLC | $1.3 million | May 6, 2020 | Jul 23, 2021 |
| 36C25520N0080 | 589-20-320: repair sewer line, building 6 (emergency) | Ljbco Group LLC | $72,520 | Dec 18, 2019 | Jan 1, 2020 |
| 36C25520P0105 | Rebuild 2 york chillers | Vazquez Commercial Contracting, LLC | $219,983 | Dec 9, 2019 | May 31, 2020 |
| 36C25520N0009 | 589-19-221 replace building 15 air handling unit | Ljbco Group LLC | $3.2 million | Oct 23, 2019 | Nov 20, 2020 |
| 36C25519P0583 | Emergent air compressor replacement | Cullum And Brown Of Kansas City Inc. | $40,647 | Jul 18, 2019 | Sep 30, 2019 |
| 36C25519P0324 | Repair multiple steam and condensation leaks | Pro-mechanical LLC | $12,078 | Apr 12, 2019 | Aug 10, 2019 |
| 36C25519P0216 | Air compressors | Cullum & Brown, Inc. | $59,857 | Jan 29, 2019 | Jul 31, 2019 |
| 36C25518N3274 | 36C25518N3274 - 589A5-17-182 replace AHUS | Wfv Construction, LLC | $5.5 million | Sep 26, 2018 | Aug 31, 2019 |
| 36C25518C0112 | 589-17-101 replace boiler controls | Saw Contracting, Inc. | $1.9 million | Mar 15, 2018 | May 1, 2020 |
| VA25515C0089 | Boiler plant inspection/testing | Destination Zero, LLC | $166,050 | Apr 1, 2015 | Mar 31, 2020 |