| 36C25226P0193 | New one time surgery chiller climacool repair for clement j zablocki VAMC (695) | Tata Express Services LLC | $120,470 | Jun 15, 2026 | Oct 15, 2026 |
| 36C25226P0418 | Emergency: bldg. 70 steam condensate pipe leak repair | Api HVAC Services, Inc. | $285,760 | Jun 12, 2026 | Sep 30, 2026 |
| 36C25226P0422 | Emergency chiller repair service. | Trane U.S. Inc. | $15,391 | May 14, 2026 | Jun 14, 2026 |
| 36C25226P0141 | Annual critical care systems test and balance for the clement j zablocki VAMC located in milwaukee wi | Winergy LLC | $49,746 | Jan 1, 2026 | Dec 31, 2030 |
| 36C24225P1372 | Emergency flash tank sensor repair | Johnson Controls, Inc | $30,385 | Aug 14, 2025 | Sep 14, 2025 |
| 36C24925P0737 | Emergency chiller repair for hospital | Johnson Controls, Inc | $68,226 | Jul 22, 2025 | Aug 8, 2025 |
| 36C25225C0042 | Emergency repair | Api HVAC Services, Inc. | $18,343 | Apr 30, 2025 | Sep 30, 2025 |
| 36C24525P0323 | Emergency VFD repair | Johnson Controls, Inc | $4,710 | Feb 12, 2025 | Feb 26, 2025 |
| 36C25225P0123 | Testing & balance of critical care areas at milwaukee VA medical center | Accustar Air Balance, Inc. | $67,900 | Jan 1, 2025 | Dec 31, 2029 |
| 36C25225P0021 | Sps and dialysis prevenative maintenance | Total Water Treatment Systems, Inc. | $242,732 | Oct 1, 2024 | Sep 30, 2027 |
| 36C25224C0046 | BLDG.7 rooftop R-22 AC units (replace 2) | Johnson Controls Government Systems, LLC | $234,221 | Sep 11, 2024 | Jul 11, 2025 |
| 36C25224P0815 | Remove and replace heat pumps | Lee Mechanical Inc | $109,556 | Jul 12, 2024 | Sep 30, 2024 |
| 36C25224P0455 | AHU replacement for the clement j zablocki VAMC | Johnson Controls, Inc | $573,900 | Apr 18, 2024 | Apr 17, 2025 |
| 36C25224P0440 | Emergency fire pump and sprinkler pipe repair | Api HVAC Services, Inc. | $15,010 | Feb 1, 2024 | Jun 6, 2024 |
| 36C24524P0246 | Sps controller | Johnson Controls, Inc | $3,661 | Dec 21, 2023 | Jan 5, 2024 |
| 36C25224P0130 | For the emergency steam line repair at the clement j. zablocki VA medical center in milwaukee wi. | Total Mechanical, Inc. | $21,500 | Oct 25, 2023 | Jan 28, 2024 |
| 36C25223C0040 | Project 695-22-107 replace building 5 AHUS | U.S. Vet General Contracting, LLC | $1.6 million | Apr 3, 2023 | Dec 14, 2024 |
| 36C25223C0039 | Project 695-22-111 replace ep lab server room AHU | Progressive Construction Services LLC | $381,832 | Apr 3, 2023 | Mar 13, 2024 |
| 36C25223P0446 | For the emergency to repair boiler # four (4) internal tube leaks at the clement j. zablocki VA medical center 5000 w national ave milwaukee, wi 53295-0001 | Pbbs Equipment Corporation | $28,340 | Jan 18, 2023 | Mar 31, 2023 |
| 36C25622P1254 | Metasys software upgrade | Johnson Controls Inc | $27,405 | Aug 18, 2022 | Sep 30, 2022 |
| 36C25221C0108 | Sealed bid award for project 695-19-104, replace fire sprinklers at the milwaukee VA. | Richard Group LLC | $1.3 million | Sep 24, 2021 | Sep 1, 2023 |
| 36C25221P1091 | Maintenance of variable frequency drives at clement zablocki VA medical center, milwaukee, wi | Jmb & Associates LLC | $627,862 | Aug 1, 2021 | Dec 31, 2025 |
| 36C25621P1236 | Emergency chiller HVAC repair services | Johnson Controls, Inc | $128,874 | Jul 9, 2021 | Aug 31, 2021 |
| 36C25221P0401 | Emergency repair of pipe with condensate leak at milwaukee VAMC, milwaukee, wi | Api HVAC Services, Inc. | $3,498 | Jun 30, 2021 | Jun 30, 2021 |
| 36C25821P0077 | Emergency replacement of chiller 4 | Johnson Controls Inc | $376,100 | Dec 17, 2020 | Mar 15, 2021 |
| 36C25220C0199 | Ifb and contract for project 695-19-114, upgrade plumbing for legionella prevention | Richard Group LLC | $8.8 million | Jul 30, 2020 | Jun 8, 2026 |
| 36C25220P0690 | Emergency condensate leak repair | Api HVAC Services, Inc. | $41,574 | May 29, 2020 | Jun 30, 2020 |
| 36C26120P0901 | Water chiller system | Johnson Controls Inc | $107,931 | Apr 21, 2020 | Jun 20, 2020 |
| 36C25220C0154 | Clean out grease traps | Milwaukee Plumbing & Piping, Inc. | $12,265 | Apr 10, 2020 | Apr 17, 2020 |
| 36C26120P0625 | Chiller rental | Johnson Controls Inc | $39,065 | Feb 26, 2020 | Mar 7, 2020 |
| 36C25220C0059 | Testing&balancing of critical care area air units | Accustar Air Balance, Inc. | $285,632 | Jan 1, 2020 | Dec 31, 2023 |
| 36C25220C0079 | Replace chiller plant building 43 mental health (SF1&SF2) at the clement j. zablocki VA medical center in milwaukee wisconsin | Veterans Electric LLC | $1.5 million | Dec 31, 2019 | Apr 12, 2021 |
| 36C25220P0093 | Emergency repair of water main pipe | Api HVAC Services, Inc. | $7,866 | Oct 7, 2019 | Jan 31, 2020 |
| 36C24120N0032 | Various HVAC filters and belts BPA | Industries For The Blind And Visually Impaired, Inc. | $45,309 | Oct 1, 2019 | Sep 30, 2020 |
| 36C25219C0222 | Project 695-16-112 building 6 sprinkler system replacement at the clement j. zablocki VA medical center, milwaukee, wi | White Star Commercial Inc. | $1.9 million | Sep 10, 2019 | Mar 6, 2023 |
| 36C25219C0175 | Project 695-16-109 upgrade V10, V11, V30 AHUS (MER2) at the clement j. zablocki VA medical center in milwaukee, wisconsin | Master Design Build LLC | $7.5 million | Jun 25, 2019 | Apr 16, 2026 |
| 36C25219P0911 | Emergency repair of water main break | Api HVAC Services, Inc. | $19,078 | May 24, 2019 | Jul 19, 2019 |
| 36C25219P0756 | Emergency repair of manhole cover | Milwaukee Plumbing & Piping, Inc. | $3,110 | Apr 11, 2019 | Jun 7, 2019 |
| 36C25219P0583 | Emergency repair of steam pipe | Milwaukee Plumbing & Piping, Inc. | $17,265 | Feb 19, 2019 | May 20, 2019 |
| 36C25219P0622 | Emergency repair of main water line | Milwaukee Plumbing & Piping, Inc. | $4,180 | Feb 19, 2019 | Apr 26, 2019 |
| 36C25219C0006 | Project 695-18-109, replace AHU building 123 kitchen at the clement j. zablocki VA medical center in milwaukee, wisconsin. | Progressive Construction Services LLC | $179,990 | Oct 10, 2018 | Jul 14, 2019 |
| 36C24119N0062 | Various HVAC filters and belts BPA | Industries For The Blind And Visually Impaired, Inc. | $55,547 | Oct 1, 2018 | Nov 8, 2019 |
| 36C25218C0219 | Fire barrier maintenance at the zablocki VA medical center, milwaukee. | Eoc Solutions LLC | $289,790 | Sep 25, 2018 | Sep 13, 2023 |
| 36C25218C0142 | Project # 695-15-116: replace 3 boilers, building 112 at clement zablocki VA medical center, milwaukee, wisconsin | Veterans Electric LLC | $9.2 million | May 1, 2018 | Jan 21, 2021 |
| 36C25218C0056 | Install EMS in sterile&clean supply rooms at the zablocki VAMC, milwaukee, wi | Progressive Construction Services LLC | $594,797 | Jan 26, 2018 | May 10, 2019 |
| VA69D17C0037 | Project 695-16-119 replace HVAC V13, AC4, MER5 at the clement j. zablocki VAMC in milwaukee, wisconsin | U.S. Vet General Contracting, LLC | $2.1 million | Dec 22, 2016 | Feb 1, 2019 |
| VA69D15C0106 | Testing and balancing of critical care systems | Accustar Air Balance, Inc. | $292,015 | Feb 10, 2015 | Dec 31, 2019 |
| VA25715P0774 | Emergency water pump repair service for dallas VAMC. | Johnson Controls, Inc | $16,576 | Jan 7, 2015 | Oct 12, 2018 |